The Chairman of the Appiatse Reconstruction Implementation Team (ARIT), Benito Owusu-Bio, has hinted that all 124 housing units at Appiatse, which forms part of the first phase of the project, are currently under various levels of construction and hopeful to be completed within the stipulated time frame.
This, he said, is an impressive work as the committee used about 4 months of the time frame given them by the government to work on the temporary structures acquired from FGR Company to provide safe shelter for the people.
Mr Benito Owusu-Bio, who is also the Deputy Minister for Lands and Natural Resources made this known when he led the Appiatse Reconstruction Implementation Team to pay a working visit to Appiatse on Wednesday, 18th January, 2023 to, among others inspect the progress of work ahead of the 1 year anniversary.
Addressing the media, the Deputy Minister explained that all contractors who were trailing behind due to marshy lands at the beginning of the construction have been relocated successfully, and that  currently, all 124 housing units, which is the core part of the Appiatse township are being constructed.
Mr Benito Owusu-Bio in his interview with the media gave a brief on government’s interventions and efforts since the incident occurred a year ago.
“We have just about two days to 20th January, which is exactly a year on since this unfortunate incident occurred and as you are aware, so far government through the Minister for lands and Natural resources, Samuel A. Jinapor has been working tirelessly to salvage the situation”.
Taking the media through the process he recapped that “government through the Ministry, NADMO and other agencies provided tents, food and basic amenities at the initial stages of the incident.
The government also had to move the people into the temporary settlement when the rains set in. The Ministry on the instructions of government also set up the Appiatse Support fund and the reconstruction team, while enforcing the safety laws to ensure that such an occurrence does not repeat itself”.
He continued that government also commiserated with the people of Appiatse and helped buried the dead while providing medical assistance for the injured.
Sticking to their promise, Benito disclosed that GETFund has also commenced the construction of a six block primary classroom and Kindergarten for children of school going age at Appiatse as their contribution towards the reconstruction of the township.
The Deputy Minister applauded their effort and called on other organisations that made similar commitments to follow the GETFund example and redeem their promise as the time to put actions to their words has come.
He indicated that road demarcations are currently underway with trenches and gutters to properly demarcate the walkways from the road and the buildings, giving the construction site better outook.
Owusu-Bio assured the media and the people of Appiatse not to fret “as government has begun this good work, it shall surely bring it to a completion as promised”
MrBlankson-Hermans, a member of the ARIT spoke to the technical details of the construction saying “so far the process is commendable because in terms of quality and speed, the most performing contractor is about 39% complete and the lowest performing contractor around 29% and considering our time frame and work schedule, I believe it’s great work and we will surely meet the time”.
He, however, hoped that the contractors will speed up work as he noted that when the rains set in, it may disrupt or delay the progress of work.
Responding to the question of government supporting some students in Appiaste to the tertiary level, the Municipal Chief Executive of the PresteaHuni Valley Municipality, IsaacDasmani said the Municipality is on top of welfare issues and so far one student has been successfully admitted at the University of Mines and Technology (UMat) with some others in the process to gain admission.